The Owner-Builder's Biggest Challenge

When you act as your own general contractor, you take on the most critical job in construction: hiring and coordinating the right subcontractors. One bad hire can cost you more than a GC would have charged.

Step 1: Verify Licensing

Utah requires licenses for specific trades:

  • General contractors (E100, B100) — required for projects over $1,000
  • Electricians — must be licensed through DOPL
  • Plumbers — must be licensed through DOPL
  • HVAC — must be licensed through DOPL

Verify any license at dopl.utah.gov. Never hire an unlicensed trade worker — you're liable for their mistakes.

Step 2: Check Insurance

Every subcontractor should carry:

  • General liability insurance — minimum $1M coverage
  • Workers' compensation — if they have employees
  • Auto insurance — for any vehicle on your site

Request certificates of insurance directly from their insurer — not copies from the contractor.

Step 3: Get Multiple Bids

For every trade, get at least three bids. But don't just compare price:

  • Scope: Are they bidding the same work? (Apples to apples)
  • Timeline: When can they start and how long will it take?
  • References: Ask for 2–3 recent project references
  • Warranty: What do they guarantee and for how long?

Step 4: Use a Pre-Vetted Network

If you don't have a rolodex of trusted trades, use a service like ContractorLink.org that connects owner-builders with pre-vetted, licensed subcontractors across Utah. This eliminates the risk of hiring blind.

Step 5: Write Clear Contracts

Every subcontractor agreement should include:

  • Detailed scope of work
  • Payment schedule (never pay 100% upfront)
  • Timeline and completion date
  • Material specifications
  • Warranty terms
  • Lien waiver requirements

Step 6: Manage the Schedule

The most common owner-builder mistake is poor trade sequencing:

  1. Excavation & foundation
  2. Plumbing & electrical rough-in
  3. Framing
  4. Windows & exterior
  5. MEP rough-in
  6. Insulation
  7. Drywall
  8. Interior finishes
  9. MEP trim
  10. Final inspection

Delays in one trade cascade to all subsequent trades. Build buffer time into your schedule.

Pro Tip

Never pay a subcontractor more than 30% upfront. Standard payment terms are 30% to start, 30% at midpoint, 30% at substantial completion, and 10% retained until final inspection and lien waiver.

Ready to Get Started?

Get a free consultation from Utah's trusted engineering and construction team.

Related Articles

How to Get a Building Permit in Utah: A Step-by-Step Guide
PermitsUtah

How to Get a Building Permit in Utah: A Step-by-Step Guide

Navigating Utah's building permit process doesn't have to be overwhelming. Here's exactly what to submit, who to talk to, and how long each step takes across Summit, Wasatch, Utah, and Salt Lake Counties.

6 min readRead
The Utah Owner-Builder Exemption: What You Need to Know
Owner-BuilderPermits

The Utah Owner-Builder Exemption: What You Need to Know

Utah allows homeowners to act as their own general contractor — saving 15–25% on construction costs. But the exemption comes with real responsibilities. Here's the complete breakdown.

7 min readRead
Topographic Surveys 101: Why Your Mountain Lot Needs One
SurveysEngineering

Topographic Surveys 101: Why Your Mountain Lot Needs One

Building on a slope in the Wasatch Back? A topographic survey is non-negotiable. Here's what it measures, what it costs, and why skipping it is the most expensive mistake you can make.

5 min readRead
V

Powered by real math, not guesswork. Every estimate on this site runs through VegaEstimating.ai, our proprietary AI-powered cost engine built specifically for custom residential construction — the reason we can hand you real numbers in days instead of six weeks.